Construction Update: Weeks of 4/5/21 and 4/12/21

View a PDF version of this week’s update

 

What is Happening

Columbia Business School

Site 7 (Western Site)

  • Completion of exterior wall glass-fiber reinforced concrete unit installations on floors 4 through 11
  • Preparation and installation of exterior glass doors is in progress
  • Interior fit-outs and overhead mechanical, electrical, and plumbing installation on floors 1 through 11
  • Three construction use cars are in service

Site 6B (Eastern Site)

  • Completion of exterior wall glass-fiber reinforced concrete unit installations on floors 2 through 8
  • Preparation and installation of exterior glass doors is in progress
  • Interior fit-outs and overhead mechanical, electrical, and plumbing installation on floors 2 through 8
  • Three construction use cars are in service

Below Grade Activity / W. 131st Street Utilities

Open Spaces between 130th and 131st Streets and along 12th Avenue

  • Stone installation of inner and outer ring
  • 12th Avenue formwork and reinforcement
  • Perimeter trench drain formwork, reinforcement, and concrete placement
  • Structural backfill is in progress
  • Electrical and low voltage conduit installation
  • Light pole pier formwork and rebar installation 

 

Please note that all activities are subject to change based on weather and other field conditions.

 

What to Expect

Construction Activity

  • Regular weekday work hours: 7:00 a.m. to 6:00 p.m. Saturday and Sunday work hours: 7:00 a.m. to 5:00 p.m. After-hours permit issued for 6:00 a.m. construction start to allow for physical distancing for workers upon entry to the site.
  • Material deliveries to site is ongoing

Temporary Traffic and Transportation Impacts